Course Registration System

C2 Iteration Plan

 

Version 1.0

 

 

Revision History

 

Date

Version

Description

Author

22/Mar/1999

1.0

Initial Plan for Construction Phase - 2nd Iteration

Rick Bell

       
       

 

Table of Contents

1.       Introduction         

1.1     Purpose     

1.2     Scope     

1.3     Definitions, Acronyms and Abbreviations     

1.4     References     

1.5     Overview     

2.       Plan      

3.       Resources

4.       Use Cases

5.       Evaluation Criteria


Iteration Plan

1.                  Introduction

1.1               Purpose

This Iteration Plan describes the detailed plans for the second iteration (C2) of the Construction Phase of the C-Registration System Project.

The first iteration (C1) of the Construction Phase developed the Beta software for Release 1 (R1.0). The second iteration (C2) of the Construction Phase will implement the remaining components for Release 1 and will fix the defects discovered in the Beta Release. The final output of this iteration will be the R1.0 software.

1.2               Scope

This C2 Iteration Plan applies to the C-Registration System project being developed by Wylie College Information Systems for Wylie College. This document will be used by the Project Manager and by the project team.

1.3               Definitions, Acronyms and Abbreviations

See the Glossary [3].

1.4               References

Applicable references are:

  1. Course Registration System Vision Document, WyIT387, V1.0, Wylie College IT.
  2. Course Registration System Stakeholder Requests Document, WyIT389, V1.0, 1998, Wylie College IT.
  3. Course Registration System Glossary, WyIT406, V1.0, 1998, Wylie College IT.
  4. Course Registration System Construction Phase Schedule, V1.0, 1999, Wylie College IT.
  5. Course Registration System Software Development Plan, WyIT418, V2.0, 1999, Wylie College IT.
  6. Course Registration System C2 Test Plan, WyIT501, V1.0, 1999, Wylie College IT.
  7. Course Registration System Supplementary Specification, WyIT400, V1.0, 1999, Wylie College IT.

 

1.5               Overview

This document provides the detailed schedule for this iteration including all milestones.  It also describes the required resources (staffing, financial, and equipment), expected status of use cases, and evaluation criteria for completion of the iteration.

2.                  Plan

The second iteration (C2) of the Construction Phase will address all defect logs and user feedback received from the Beta Release. C2 will also implement remaining use cases, classes, and components that did not make it into the Beta Release. C2 will result in fully operational software for Release 1 (R1.0).

The duration of the second iteration (C2) is approximately one month.

The primary use cases that form Release 1.0 are shown below.

    1. Iteration Tasks

The following table illustrates the high level activities for C2 with their planned start and end dates.

Activity

Start Date

End Date

Analysis & Design (Remaining R1 use cases & defects)

April 16, 1999

April 26, 1999

Implementation (R1 & Beta defects)

April 16, 1999

May 6, 1999

Test (R1 & Beta defects)

April 16, 1999

May 12, 1999

Environment

April 13, 1999

May 14, 1999

Management

April 13, 1999

May 14, 1999

    1. Iteration Schedule

The detailed schedule showing all tasks and the assigned responsibilities is contained in the following schedule [4]:

 

Task Name

Start

Finish

Resource Names

Milestones

Mon 3/15/99

Thu 6/17/99

 

Start Construction Iteration 1

Mon 3/15/99

Mon 3/15/99

 

R1 Beta Milestone (Beta Software Ready)

Mon 4/12/99

Mon 4/12/99

 

Start Construction Iteration 2

Mon 4/12/99

Mon 4/12/99

 

Initial Operational Capability Milestone (Release 1.0)

Fri 5/14/99

Fri 5/14/99

 

Start Construction Iteration 3

Fri 5/14/99

Fri 5/14/99

 

Second Operational Capability Milestone (Release 2.0)

Thu 6/17/99

Thu 6/17/99

 
 
 
 
 
 
 
 
 

Construction Phase

Mon 3/15/99

Thu 6/17/99

 

Iteration C1 - Develop Release 1 Beta

Mon 3/15/99

Mon 4/12/99

 

Analysis & Design (Refine)

Tue 3/16/99

Thu 3/25/99

 

Refine Architecture

Mon 3/22/99

Thu 3/25/99

Architect

Prioritized Subsystem Design

Tue 3/16/99

Wed 3/17/99

 

Subsystem Design - Subsystem ss-fx

Tue 3/16/99

Wed 3/17/99

Designer

Subsystem Design - Subsystem ss-cr

Tue 3/16/99

Wed 3/17/99

Designer

Prioritized Class Design

Tue 3/16/99

Wed 3/17/99

 

Class Design - Class C-brx

Tue 3/16/99

Wed 3/17/99

Designer

Class Design - Class C-abx

Tue 3/16/99

Wed 3/17/99

Designer

Class Design - Class C-twe

Tue 3/16/99

Wed 3/17/99

Designer

Class Design - Class C-tui

Tue 3/16/99

Wed 3/17/99

Designer

Prioritized Use-Case Design

Thu 3/18/99

Fri 3/19/99

 

Design Use-Case uc-hev

Thu 3/18/99

Fri 3/19/99

Designer

Design Use-Case uc-mrk

Thu 3/18/99

Fri 3/19/99

Designer

Database Design

Mon 3/22/99

Tue 3/23/99

Database Designer

Review the Design

Wed 3/24/99

Thu 3/25/99

Design Reviewer

Implementation (Beta)

Tue 3/16/99

Tue 4/6/99

 

Plan System Integration

Tue 3/16/99

Wed 3/17/99

System Integrator

Plan Subsystem Integration

Thu 3/18/99

Fri 3/19/99

Implementer

Implement Prioritized Components

Mon 3/22/99

Tue 3/23/99

 

Implement Component c-uic

Mon 3/22/99

Tue 3/23/99

Implementer

Implement Component c-uib

Mon 3/22/99

Tue 3/23/99

Implementer

Implement Component c-iln

Mon 3/22/99

Tue 3/23/99

Implementer

Implement Component c-oie

Mon 3/22/99

Tue 3/23/99

Implementer

Implement Component c-wes

Mon 3/22/99

Tue 3/23/99

Implementer

Implement Component c-kkm

Mon 3/22/99

Tue 3/23/99

Implementer

Fix Defects

Mon 3/22/99

Wed 3/24/99

Implementer

Review Code

Thu 3/25/99

Fri 3/26/99

Code Reviewer

Perform Unit Tests

Thu 3/25/99

Mon 3/29/99

Implementer

Integrate Subsystem

Tue 3/30/99

Thu 4/1/99

Implementer

Integrate System

Fri 4/2/99

Tue 4/6/99

System Integrator

Test (Interfaces & Integrated Function)

Tue 3/16/99

Thu 4/8/99

 

Plan Test (Integration & System)

Tue 3/16/99

Tue 3/16/99

Test Designer

Design Test (Integration & System)

Wed 3/17/99

Wed 3/17/99

Test Designer

Implement Test

Thu 3/18/99

Thu 3/18/99

Test Designer

Design Test Packages and Classes

Fri 3/19/99

Fri 3/19/99

Designer

Implement Test Components and Subsystems

Mon 3/22/99

Mon 3/22/99

Implementer

Execute Integration Tests

Fri 4/2/99

Fri 4/2/99

Integration Tester

Execute System Test

Wed 4/7/99

Wed 4/7/99

System Tester

Execute Performance Tests

Tue 3/23/99

Tue 3/23/99

Performance Tester

Evaluate Test

Thu 4/8/99

Thu 4/8/99

Test Designer

Management

Mon 3/15/99

Mon 4/12/99

 

Develop Iteration Plan

Mon 3/15/99

Mon 3/15/99

Project Manager

Staff Project

Tue 3/16/99

Tue 3/16/99

Project Manager

Revisit Risk List

Mon 3/15/99

Mon 3/29/99

Project Manager

Evaluate the Iteration

Fri 4/9/99

Fri 4/9/99

Project Manager

Update Project Plan

Mon 4/12/99

Mon 4/12/99

Project Manager

Iteration C2 - Develop Release 1

Tue 4/13/99

Fri 5/14/99

 

Analysis & Design (Refine)

Fri 4/16/99

Mon 4/26/99

 

Refine Architecture

Mon 4/26/99

Mon 4/26/99

Architect

Prioritized Subsystem Design

Fri 4/16/99

Mon 4/19/99

Designer

Subsystem Design - Subsystem ss-inf

Fri 4/16/99

Mon 4/19/99

 

Subsystem Design - Subsystem ss-ext

Fri 4/16/99

Mon 4/19/99

 

Prioritized Class Design

Fri 4/16/99

Mon 4/19/99

 

Class Design - Class C-imn

Fri 4/16/99

Mon 4/19/99

Designer

Class Design - Class C-ppl

Fri 4/16/99

Mon 4/19/99

Designer

Class Design - Class C-pnh

Fri 4/16/99

Mon 4/19/99

Designer

Class Design - Class C-ujn

Fri 4/16/99

Mon 4/19/99

Designer

Prioritized Use-Case Design

Tue 4/20/99

Wed 4/21/99

Designer

Design Use-Case uc-wsx

Tue 4/20/99

Wed 4/21/99

Designer

Design Use-Case uc-vbc

Tue 4/20/99

Wed 4/21/99

Designer

Database Design

Thu 4/22/99

Thu 4/22/99

Database Designer

Review the Design

Fri 4/23/99

Mon 4/26/99

Design Reviewer

Implementation (Effective Production)

Fri 4/16/99

Thu 5/6/99

 

Plan System Integration

Fri 4/16/99

Mon 4/19/99

System Integrator

Plan Subsystem Integration

Tue 4/20/99

Wed 4/21/99

Implementer

Implement Prioritized Components

Thu 4/22/99

Fri 4/23/99

 

Implement Component c-red

Thu 4/22/99

Fri 4/23/99

Implementer

Implement Component c-art

Thu 4/22/99

Fri 4/23/99

Implementer

Implement Component c-had

Thu 4/22/99

Fri 4/23/99

Implementer

Implement Component c-unv

Thu 4/22/99

Fri 4/23/99

Implementer

Implement Component c-tak

Thu 4/22/99

Fri 4/23/99

Implementer

Implement Component c-fin

Thu 4/22/99

Fri 4/23/99

Implementer

Fix Defects

Thu 4/22/99

Fri 4/23/99

Implementer

Review Code

Mon 4/26/99

Wed 4/28/99

Code Reviewer

Perform Unit Tests

Mon 4/26/99

Wed 4/28/99

Implementer

Integrate Subsystem

Thu 4/29/99

Mon 5/3/99

Implementer

Integrate System

Tue 5/4/99

Thu 5/6/99

System Integrator

Test (Interfaces & Integrated Function)

Fri 4/16/99

Wed 5/12/99

 

Plan Test (Integration & System)

Fri 4/16/99

Mon 4/19/99

Test Designer

Design Test (Integration & System)

Tue 4/20/99

Wed 4/21/99

Test Designer

Implement Test

Thu 4/22/99

Mon 4/26/99

Test Designer

Design Test Packages and Classes

Tue 4/27/99

Thu 4/29/99

Designer

Implement Test Components and Subsystems

Fri 4/30/99

Tue 5/4/99

Implementer

Execute Integration Tests

Wed 5/5/99

Fri 5/7/99

Integration Tester

Execute System Test

Fri 5/7/99

Tue 5/11/99

System Tester

Execute Performance Tests

Wed 5/5/99

Fri 5/7/99

Performance Tester

Evaluate Test

Wed 5/12/99

Wed 5/12/99

Test Designer

Management

Tue 4/13/99

Fri 5/14/99

 

Develop Iteration Plan

Tue 4/13/99

Thu 4/15/99

Project Manager

Staff Project

Fri 4/16/99

Fri 4/16/99

Project Manager

Revisit Risk List

Tue 4/13/99

Tue 4/27/99

Project Manager

Evaluate the Iteration

Thu 5/13/99

Thu 5/13/99

Project Manager

Update Project Plan

Fri 5/14/99

Fri 5/14/99

Project Manager

Iteration C3 - Develop Release 2.0

Mon 5/17/99

Thu 6/17/99

 

Analysis & Design (Refine)

Wed 5/19/99

Wed 5/26/99

 

Refine Architecture

Tue 5/25/99

Wed 5/26/99

Architect

Prioritized Subsystem Design

Wed 5/19/99

Thu 5/20/99

Designer

Subsystem Design - Subsystem ss-new

Wed 5/19/99

Thu 5/20/99

 

Prioritized Class Design

Wed 5/19/99

Thu 5/20/99

 

Class Design - Class C-vad

Wed 5/19/99

Thu 5/20/99

Designer

Class Design - Class C-jud

Wed 5/19/99

Thu 5/20/99

Designer

Class Design - Class C-pol

Wed 5/19/99

Thu 5/20/99

Designer

Class Design - Class C-pat

Wed 5/19/99

Thu 5/20/99

Designer

Prioritized Use-Case Design

Fri 5/21/99

Mon 5/24/99

Designer

Design Use-Case uc-cad

Fri 5/21/99

Mon 5/24/99

Designer

Database Design

Tue 5/25/99

Tue 5/25/99

Database Designer

Review the Design

Wed 5/26/99

Wed 5/26/99

Design Reviewer

Implementation (Effective Production)

Wed 5/19/99

Wed 6/9/99

 

Plan System Integration

Wed 5/19/99

Thu 5/20/99

System Integrator

Plan Subsystem Integration

Fri 5/21/99

Mon 5/24/99

Implementer

Implement Prioritized Components

Tue 5/25/99

Wed 5/26/99

 

Implement Component c-rad

Tue 5/25/99

Wed 5/26/99

Implementer

Implement Component c-bpp

Tue 5/25/99

Wed 5/26/99

Implementer

Implement Component c-puj

Tue 5/25/99

Wed 5/26/99

Implementer

Implement Component c-hbn

Tue 5/25/99

Wed 5/26/99

Implementer

Implement Component c-cdd

Tue 5/25/99

Wed 5/26/99

Implementer

Implement Component c-fer

Tue 5/25/99

Wed 5/26/99

Implementer

Fix Defects

Tue 5/25/99

Thu 5/27/99

Implementer

Review Code

Fri 5/28/99

Mon 5/31/99

Code Reviewer

Perform Unit Tests

Fri 5/28/99

Tue 6/1/99

Implementer

Integrate Subsystem

Wed 6/2/99

Fri 6/4/99

Implementer

Integrate System

Mon 6/7/99

Wed 6/9/99

System Integrator

Test (Interfaces & Integrated Function)

Wed 5/19/99

Tue 6/15/99

 

Plan Test (Integration & System)

Wed 5/19/99

Thu 5/20/99

Test Designer

Design Test (Integration & System)

Fri 5/21/99

Mon 5/24/99

Test Designer

Implement Test

Tue 5/25/99

Thu 5/27/99

Test Designer

Design Test Packages and Classes

Fri 5/28/99

Mon 5/31/99

Designer

Implement Test Components and Subsystems

Tue 6/1/99

Wed 6/2/99

Implementer

Execute Integration Tests

Mon 6/7/99

Wed 6/9/99

Integration Tester

Execute System Test

Thu 6/10/99

Mon 6/14/99

System Tester

Execute Performance Tests

Thu 6/3/99

Mon 6/7/99

Performance Tester

Evaluate Test

Tue 6/15/99

Tue 6/15/99

Test Designer

Management

Mon 5/17/99

Thu 6/17/99

 

Develop Iteration Plan

Mon 5/17/99

Tue 5/18/99

Project Manager

Staff Project

Wed 5/19/99

Wed 5/19/99

Project Manager

Revisit Risk List

Mon 5/17/99

Mon 5/31/99

Project Manager

Evaluate the Iteration

Wed 6/16/99

Wed 6/16/99

Project Manager

Update Project Plan

Thu 6/17/99

Thu 6/17/99

Project Manager

 
 
 
 

Environment

Mon 3/15/99

Thu 6/17/99

 

Support the Development

Mon 3/15/99

Thu 6/17/99

 
    1. Iteration Deliverables

The following deliverables will be generated and reviewed during the second iteration (C2) of the Construction Phase:

Process

Deliverable

Responsible Owner

Design Set

Analysis Model (update)

Design Model (update)

Software Architecture Document (update)

Sue Gamble

Beth MacDonald

Steve Johnson

Implementation Set

Integration Build Plan

R1.0 Software Baseline

Test Drivers, Stubs, Data, & Scripts

Test Evaluation Report

Kerry Stone

Phil Johnson

Simon Jones

Carol Smith

Management Set

C2 Iteration Plan

Project Plan (update)

Project Schedule (update)

Project Risk List (update)

Status Assessment

Iteration Assessment

Test Plan

Rick Bell

Rick Bell

Rick Bell

Rick Bell

Rick Bell

Rick Bell

Kerry Stone

 

3.                  Resources

Resources

    1. Equipment & Facilities Resources

The C2 Iteration requires the following computer equipment:

-         18 PCs (Microsoft Windows 95 , Microsoft Office, Rational Rose, Rational RequisitePro)

-         20 Monitors

-         3 Printers (2 Laser, 1 Color)

-         Access to the Wylie College Server.

This equipment is already in place at Wylie College Information Systems. Equipment required exclusively for Test will be detailed in the Test Plan.

Office space needs to be setup for the 2 new hires.

4.                  Use Cases

No new use cases will be developed for the C2 Iteration as the previous iteration (C1) to produce the Beta brought in the remaining Release 1.0 use cases. However, the following existing use cases require extensive rework:

1.        Close Registration

2.        Interface to Course Catalog Database

3.        Interface to Finance System

5.                  Evaluation Criteria

The primary goal of the C2 Iteration of the Construction Phase is to complete the software baseline for Release 1 (R1.0). The R1.0 baseline must be available for the Deployment Team no later than May 20th, 1999.

In addition, the following criteria must be met prior to completion of the C2 Iteration:

-         All critical, high, and medium priority defects discovered in the Beta Release (from C1 Iteration) must be resolved.

-         All user feedback from the Beta Release must be evaluated. All feedback classified as "major" must be resolved.

-         All use cases and requirements targeted for Release 1 must be implemented and tested.

-         All timing, performance, and quality requirements, as specified in the Supplementary Specification [7], must be met.

-         The Tests, as defined in the Test Plan [6], must be executed.

-         All test results must be reviewed.

-         The senior management team and the Wylie College representative must approve the release of the R1.0 software baseline.