C2 Iteration Plan
Version 1.0
Revision History
Date |
Version |
Description |
Author |
---|---|---|---|
22/Mar/1999 |
1.0 |
Initial Plan for Construction Phase - 2nd Iteration |
Rick Bell |
Table of Contents
1.3 Definitions, Acronyms and Abbreviations
Iteration Plan
This Iteration Plan describes the detailed plans for the second iteration (C2) of the Construction Phase of the C-Registration System Project.
The first iteration (C1) of the Construction Phase developed the Beta software for Release 1 (R1.0). The second iteration (C2) of the Construction Phase will implement the remaining components for Release 1 and will fix the defects discovered in the Beta Release. The final output of this iteration will be the R1.0 software.
This C2 Iteration Plan applies to the C-Registration System project being developed by Wylie College Information Systems for Wylie College. This document will be used by the Project Manager and by the project team.
See the Glossary [3].
Applicable references are:
This document provides the detailed schedule for this iteration including all milestones. It also describes the required resources (staffing, financial, and equipment), expected status of use cases, and evaluation criteria for completion of the iteration.
The second iteration (C2) of the Construction Phase will address all defect logs and user feedback received from the Beta Release. C2 will also implement remaining use cases, classes, and components that did not make it into the Beta Release. C2 will result in fully operational software for Release 1 (R1.0).
The duration of the second iteration (C2) is approximately one month.
The primary use cases that form Release 1.0 are shown below.
The following table illustrates the high level activities for C2 with their planned start and end dates.
Activity |
Start Date |
End Date |
---|---|---|
Analysis & Design (Remaining R1 use cases & defects) |
April 16, 1999 |
April 26, 1999 |
Implementation (R1 & Beta defects) |
April 16, 1999 |
May 6, 1999 |
Test (R1 & Beta defects) |
April 16, 1999 |
May 12, 1999 |
Environment |
April 13, 1999 |
May 14, 1999 |
Management |
April 13, 1999 |
May 14, 1999 |
The detailed schedule showing all tasks and the assigned responsibilities is contained in the following schedule [4]:
|
|
|
|
---|---|---|---|
Milestones |
Mon 3/15/99 |
Thu 6/17/99 |
|
Start Construction Iteration 1 |
Mon 3/15/99 |
Mon 3/15/99 |
|
R1 Beta Milestone (Beta Software Ready) |
Mon 4/12/99 |
Mon 4/12/99 |
|
Start Construction Iteration 2 |
Mon 4/12/99 |
Mon 4/12/99 |
|
Initial Operational Capability Milestone (Release 1.0) |
Fri 5/14/99 |
Fri 5/14/99 |
|
Start Construction Iteration 3 |
Fri 5/14/99 |
Fri 5/14/99 |
|
Second Operational Capability Milestone (Release 2.0) |
Thu 6/17/99 |
Thu 6/17/99 |
|
|
|
|
|
|
|
|
|
Construction Phase |
Mon 3/15/99 |
Thu 6/17/99 |
|
Iteration C1 - Develop Release 1 Beta |
Mon 3/15/99 |
Mon 4/12/99 |
|
Analysis & Design (Refine) |
Tue 3/16/99 |
Thu 3/25/99 |
|
Refine Architecture |
Mon 3/22/99 |
Thu 3/25/99 |
Architect |
Prioritized Subsystem Design |
Tue 3/16/99 |
Wed 3/17/99 |
|
Subsystem Design - Subsystem ss-fx |
Tue 3/16/99 |
Wed 3/17/99 |
Designer |
Subsystem Design - Subsystem ss-cr |
Tue 3/16/99 |
Wed 3/17/99 |
Designer |
Prioritized Class Design |
Tue 3/16/99 |
Wed 3/17/99 |
|
Class Design - Class C-brx |
Tue 3/16/99 |
Wed 3/17/99 |
Designer |
Class Design - Class C-abx |
Tue 3/16/99 |
Wed 3/17/99 |
Designer |
Class Design - Class C-twe |
Tue 3/16/99 |
Wed 3/17/99 |
Designer |
Class Design - Class C-tui |
Tue 3/16/99 |
Wed 3/17/99 |
Designer |
Prioritized Use-Case Design |
Thu 3/18/99 |
Fri 3/19/99 |
|
Design Use-Case uc-hev |
Thu 3/18/99 |
Fri 3/19/99 |
Designer |
Design Use-Case uc-mrk |
Thu 3/18/99 |
Fri 3/19/99 |
Designer |
Database Design |
Mon 3/22/99 |
Tue 3/23/99 |
Database Designer |
Review the Design |
Wed 3/24/99 |
Thu 3/25/99 |
Design Reviewer |
Implementation (Beta) |
Tue 3/16/99 |
Tue 4/6/99 |
|
Plan System Integration |
Tue 3/16/99 |
Wed 3/17/99 |
System Integrator |
Plan Subsystem Integration |
Thu 3/18/99 |
Fri 3/19/99 |
Implementer |
Implement Prioritized Components |
Mon 3/22/99 |
Tue 3/23/99 |
|
Implement Component c-uic |
Mon 3/22/99 |
Tue 3/23/99 |
Implementer |
Implement Component c-uib |
Mon 3/22/99 |
Tue 3/23/99 |
Implementer |
Implement Component c-iln |
Mon 3/22/99 |
Tue 3/23/99 |
Implementer |
Implement Component c-oie |
Mon 3/22/99 |
Tue 3/23/99 |
Implementer |
Implement Component c-wes |
Mon 3/22/99 |
Tue 3/23/99 |
Implementer |
Implement Component c-kkm |
Mon 3/22/99 |
Tue 3/23/99 |
Implementer |
Fix Defects |
Mon 3/22/99 |
Wed 3/24/99 |
Implementer |
Review Code |
Thu 3/25/99 |
Fri 3/26/99 |
Code Reviewer |
Perform Unit Tests |
Thu 3/25/99 |
Mon 3/29/99 |
Implementer |
Integrate Subsystem |
Tue 3/30/99 |
Thu 4/1/99 |
Implementer |
Integrate System |
Fri 4/2/99 |
Tue 4/6/99 |
System Integrator |
Test (Interfaces & Integrated Function) |
Tue 3/16/99 |
Thu 4/8/99 |
|
Plan Test (Integration & System) |
Tue 3/16/99 |
Tue 3/16/99 |
Test Designer |
Design Test (Integration & System) |
Wed 3/17/99 |
Wed 3/17/99 |
Test Designer |
Implement Test |
Thu 3/18/99 |
Thu 3/18/99 |
Test Designer |
Design Test Packages and Classes |
Fri 3/19/99 |
Fri 3/19/99 |
Designer |
Implement Test Components and Subsystems |
Mon 3/22/99 |
Mon 3/22/99 |
Implementer |
Execute Integration Tests |
Fri 4/2/99 |
Fri 4/2/99 |
Integration Tester |
Execute System Test |
Wed 4/7/99 |
Wed 4/7/99 |
System Tester |
Execute Performance Tests |
Tue 3/23/99 |
Tue 3/23/99 |
Performance Tester |
Evaluate Test |
Thu 4/8/99 |
Thu 4/8/99 |
Test Designer |
Management |
Mon 3/15/99 |
Mon 4/12/99 |
|
Develop Iteration Plan |
Mon 3/15/99 |
Mon 3/15/99 |
Project Manager |
Staff Project |
Tue 3/16/99 |
Tue 3/16/99 |
Project Manager |
Revisit Risk List |
Mon 3/15/99 |
Mon 3/29/99 |
Project Manager |
Evaluate the Iteration |
Fri 4/9/99 |
Fri 4/9/99 |
Project Manager |
Update Project Plan |
Mon 4/12/99 |
Mon 4/12/99 |
Project Manager |
Iteration C2 - Develop Release 1 |
Tue 4/13/99 |
Fri 5/14/99 |
|
Analysis & Design (Refine) |
Fri 4/16/99 |
Mon 4/26/99 |
|
Refine Architecture |
Mon 4/26/99 |
Mon 4/26/99 |
Architect |
Prioritized Subsystem Design |
Fri 4/16/99 |
Mon 4/19/99 |
Designer |
Subsystem Design - Subsystem ss-inf |
Fri 4/16/99 |
Mon 4/19/99 |
|
Subsystem Design - Subsystem ss-ext |
Fri 4/16/99 |
Mon 4/19/99 |
|
Prioritized Class Design |
Fri 4/16/99 |
Mon 4/19/99 |
|
Class Design - Class C-imn |
Fri 4/16/99 |
Mon 4/19/99 |
Designer |
Class Design - Class C-ppl |
Fri 4/16/99 |
Mon 4/19/99 |
Designer |
Class Design - Class C-pnh |
Fri 4/16/99 |
Mon 4/19/99 |
Designer |
Class Design - Class C-ujn |
Fri 4/16/99 |
Mon 4/19/99 |
Designer |
Prioritized Use-Case Design |
Tue 4/20/99 |
Wed 4/21/99 |
Designer |
Design Use-Case uc-wsx |
Tue 4/20/99 |
Wed 4/21/99 |
Designer |
Design Use-Case uc-vbc |
Tue 4/20/99 |
Wed 4/21/99 |
Designer |
Database Design |
Thu 4/22/99 |
Thu 4/22/99 |
Database Designer |
Review the Design |
Fri 4/23/99 |
Mon 4/26/99 |
Design Reviewer |
Implementation (Effective Production) |
Fri 4/16/99 |
Thu 5/6/99 |
|
Plan System Integration |
Fri 4/16/99 |
Mon 4/19/99 |
System Integrator |
Plan Subsystem Integration |
Tue 4/20/99 |
Wed 4/21/99 |
Implementer |
Implement Prioritized Components |
Thu 4/22/99 |
Fri 4/23/99 |
|
Implement Component c-red |
Thu 4/22/99 |
Fri 4/23/99 |
Implementer |
Implement Component c-art |
Thu 4/22/99 |
Fri 4/23/99 |
Implementer |
Implement Component c-had |
Thu 4/22/99 |
Fri 4/23/99 |
Implementer |
Implement Component c-unv |
Thu 4/22/99 |
Fri 4/23/99 |
Implementer |
Implement Component c-tak |
Thu 4/22/99 |
Fri 4/23/99 |
Implementer |
Implement Component c-fin |
Thu 4/22/99 |
Fri 4/23/99 |
Implementer |
Fix Defects |
Thu 4/22/99 |
Fri 4/23/99 |
Implementer |
Review Code |
Mon 4/26/99 |
Wed 4/28/99 |
Code Reviewer |
Perform Unit Tests |
Mon 4/26/99 |
Wed 4/28/99 |
Implementer |
Integrate Subsystem |
Thu 4/29/99 |
Mon 5/3/99 |
Implementer |
Integrate System |
Tue 5/4/99 |
Thu 5/6/99 |
System Integrator |
Test (Interfaces & Integrated Function) |
Fri 4/16/99 |
Wed 5/12/99 |
|
Plan Test (Integration & System) |
Fri 4/16/99 |
Mon 4/19/99 |
Test Designer |
Design Test (Integration & System) |
Tue 4/20/99 |
Wed 4/21/99 |
Test Designer |
Implement Test |
Thu 4/22/99 |
Mon 4/26/99 |
Test Designer |
Design Test Packages and Classes |
Tue 4/27/99 |
Thu 4/29/99 |
Designer |
Implement Test Components and Subsystems |
Fri 4/30/99 |
Tue 5/4/99 |
Implementer |
Execute Integration Tests |
Wed 5/5/99 |
Fri 5/7/99 |
Integration Tester |
Execute System Test |
Fri 5/7/99 |
Tue 5/11/99 |
System Tester |
Execute Performance Tests |
Wed 5/5/99 |
Fri 5/7/99 |
Performance Tester |
Evaluate Test |
Wed 5/12/99 |
Wed 5/12/99 |
Test Designer |
Management |
Tue 4/13/99 |
Fri 5/14/99 |
|
Develop Iteration Plan |
Tue 4/13/99 |
Thu 4/15/99 |
Project Manager |
Staff Project |
Fri 4/16/99 |
Fri 4/16/99 |
Project Manager |
Revisit Risk List |
Tue 4/13/99 |
Tue 4/27/99 |
Project Manager |
Evaluate the Iteration |
Thu 5/13/99 |
Thu 5/13/99 |
Project Manager |
Update Project Plan |
Fri 5/14/99 |
Fri 5/14/99 |
Project Manager |
Iteration C3 - Develop Release 2.0 |
Mon 5/17/99 |
Thu 6/17/99 |
|
Analysis & Design (Refine) |
Wed 5/19/99 |
Wed 5/26/99 |
|
Refine Architecture |
Tue 5/25/99 |
Wed 5/26/99 |
Architect |
Prioritized Subsystem Design |
Wed 5/19/99 |
Thu 5/20/99 |
Designer |
Subsystem Design - Subsystem ss-new |
Wed 5/19/99 |
Thu 5/20/99 |
|
Prioritized Class Design |
Wed 5/19/99 |
Thu 5/20/99 |
|
Class Design - Class C-vad |
Wed 5/19/99 |
Thu 5/20/99 |
Designer |
Class Design - Class C-jud |
Wed 5/19/99 |
Thu 5/20/99 |
Designer |
Class Design - Class C-pol |
Wed 5/19/99 |
Thu 5/20/99 |
Designer |
Class Design - Class C-pat |
Wed 5/19/99 |
Thu 5/20/99 |
Designer |
Prioritized Use-Case Design |
Fri 5/21/99 |
Mon 5/24/99 |
Designer |
Design Use-Case uc-cad |
Fri 5/21/99 |
Mon 5/24/99 |
Designer |
Database Design |
Tue 5/25/99 |
Tue 5/25/99 |
Database Designer |
Review the Design |
Wed 5/26/99 |
Wed 5/26/99 |
Design Reviewer |
Implementation (Effective Production) |
Wed 5/19/99 |
Wed 6/9/99 |
|
Plan System Integration |
Wed 5/19/99 |
Thu 5/20/99 |
System Integrator |
Plan Subsystem Integration |
Fri 5/21/99 |
Mon 5/24/99 |
Implementer |
Implement Prioritized Components |
Tue 5/25/99 |
Wed 5/26/99 |
|
Implement Component c-rad |
Tue 5/25/99 |
Wed 5/26/99 |
Implementer |
Implement Component c-bpp |
Tue 5/25/99 |
Wed 5/26/99 |
Implementer |
Implement Component c-puj |
Tue 5/25/99 |
Wed 5/26/99 |
Implementer |
Implement Component c-hbn |
Tue 5/25/99 |
Wed 5/26/99 |
Implementer |
Implement Component c-cdd |
Tue 5/25/99 |
Wed 5/26/99 |
Implementer |
Implement Component c-fer |
Tue 5/25/99 |
Wed 5/26/99 |
Implementer |
Fix Defects |
Tue 5/25/99 |
Thu 5/27/99 |
Implementer |
Review Code |
Fri 5/28/99 |
Mon 5/31/99 |
Code Reviewer |
Perform Unit Tests |
Fri 5/28/99 |
Tue 6/1/99 |
Implementer |
Integrate Subsystem |
Wed 6/2/99 |
Fri 6/4/99 |
Implementer |
Integrate System |
Mon 6/7/99 |
Wed 6/9/99 |
System Integrator |
Test (Interfaces & Integrated Function) |
Wed 5/19/99 |
Tue 6/15/99 |
|
Plan Test (Integration & System) |
Wed 5/19/99 |
Thu 5/20/99 |
Test Designer |
Design Test (Integration & System) |
Fri 5/21/99 |
Mon 5/24/99 |
Test Designer |
Implement Test |
Tue 5/25/99 |
Thu 5/27/99 |
Test Designer |
Design Test Packages and Classes |
Fri 5/28/99 |
Mon 5/31/99 |
Designer |
Implement Test Components and Subsystems |
Tue 6/1/99 |
Wed 6/2/99 |
Implementer |
Execute Integration Tests |
Mon 6/7/99 |
Wed 6/9/99 |
Integration Tester |
Execute System Test |
Thu 6/10/99 |
Mon 6/14/99 |
System Tester |
Execute Performance Tests |
Thu 6/3/99 |
Mon 6/7/99 |
Performance Tester |
Evaluate Test |
Tue 6/15/99 |
Tue 6/15/99 |
Test Designer |
Management |
Mon 5/17/99 |
Thu 6/17/99 |
|
Develop Iteration Plan |
Mon 5/17/99 |
Tue 5/18/99 |
Project Manager |
Staff Project |
Wed 5/19/99 |
Wed 5/19/99 |
Project Manager |
Revisit Risk List |
Mon 5/17/99 |
Mon 5/31/99 |
Project Manager |
Evaluate the Iteration |
Wed 6/16/99 |
Wed 6/16/99 |
Project Manager |
Update Project Plan |
Thu 6/17/99 |
Thu 6/17/99 |
Project Manager |
|
|
|
|
Environment |
Mon 3/15/99 |
Thu 6/17/99 |
|
Support the Development |
Mon 3/15/99 |
Thu 6/17/99 |
|
The following deliverables will be generated and reviewed during the second iteration (C2) of the Construction Phase:
Process |
Deliverable |
Responsible Owner |
---|---|---|
Design Set |
Analysis Model (update) Design Model (update) Software Architecture Document (update) |
Sue Gamble Beth MacDonald Steve Johnson |
Implementation Set |
Integration Build Plan R1.0 Software Baseline Test Drivers, Stubs, Data, & Scripts Test Evaluation Report |
Kerry Stone Phil Johnson Simon Jones Carol Smith |
Management Set |
C2 Iteration Plan Project Plan (update) Project Schedule (update) Project Risk List (update) Status Assessment Iteration Assessment Test Plan |
Rick Bell Rick Bell Rick Bell Rick Bell Rick Bell Rick Bell Kerry Stone |
The C2 Iteration requires the following computer equipment:
- 18 PCs (Microsoft Windows 95 , Microsoft Office, Rational Rose, Rational RequisitePro)
- 20 Monitors
- 3 Printers (2 Laser, 1 Color)
- Access to the Wylie College Server.
This equipment is already in place at Wylie College Information Systems. Equipment required exclusively for Test will be detailed in the Test Plan.
Office space needs to be setup for the 2 new hires.
No new use cases will be developed for the C2 Iteration as the previous iteration (C1) to produce the Beta brought in the remaining Release 1.0 use cases. However, the following existing use cases require extensive rework:
1. Close Registration
2. Interface to Course Catalog Database
3. Interface to Finance System
The primary goal of the C2 Iteration of the Construction Phase is to complete the software baseline for Release 1 (R1.0). The R1.0 baseline must be available for the Deployment Team no later than May 20th, 1999.
In addition, the following criteria must be met prior to completion of the C2 Iteration:
- All critical, high, and medium priority defects discovered in the Beta Release (from C1 Iteration) must be resolved.
- All user feedback from the Beta Release must be evaluated. All feedback classified as "major" must be resolved.
- All use cases and requirements targeted for Release 1 must be implemented and tested.
- All timing, performance, and quality requirements, as specified in the Supplementary Specification [7], must be met.
- The Tests, as defined in the Test Plan [6], must be executed.
- All test results must be reviewed.
- The senior management team and the Wylie College representative must approve the release of the R1.0 software baseline.